719-725 W. Pratt St. construction updates

Saturday, December 11, 2021

Sunday work crew

Due to the complexities of closing Pratt St. during the work week, the construction crew at 733 Pratt will be working this Sunday (Dec. 12). They apologize for the inconvenience.

Tuesday, November 30, 2021

Demotion schedule

Partial demolition of the buildings along the 700 block of Pratt St. will begin on Thursday, Dec. 2. Immediate neighbors do not need to take any precautions during demolition. It may take up to a week or more for completion due to the delicate nature of the project. Rodent mitigation and treatment has been completed prior to the work being done this week.

Tuesday, November 30, 2021

Demotion schedule

Partial demolition of the buildings at 733-737 West Pratt St. will begin on Thursday, Dec. 2. Immediate neighbors do not need to take any precautions during demolition. It may take up to a week or more for completion due to the delicate nature of the project. Facades of the buildings are being saved. Rodent mitigation and treatment was completed prior to the work being done this week.

Thursday, September 16, 2021

Dover Street closures to end

The work that required Dover Street to be closed should end today. Look for a future update on the return of the cobblestones.

Tuesday, September 7, 2021

Notice for 700 Block of Dover St.

Ongoing construction work will require the 700 block of Dover St. to be closed on Wednesday, Sept 9, Thursday, Sept. 10th and Monday, Sept. 13th. The developer is aware of garbage pickup on Wednesdays and will try to accommodate trash removal. Residents who live on the corner of Fremont and Dover will still be able to access the parking lot behind their houses, but they must enter and exit from Fremont Ave. instead of Dover. The developer apologizes for the inconvenience.

Thursday, July 22, 2021

Dover Street closures continue

Work that requires the 700 block of Dover St. to be closed will unfortunately continue tomorrow (Friday) and Monday. It is taking longer than originally expected.

Monday, July 19, 2021

Change in schedule

The 700 block of Dover St. will remain open today (July 19). The subcontractor had to push the conduit street work until tomorrow, (July 20) and Wednesday (June 21). The project manager apologizes for the change.

Wednesday, July 14, 2021

Extended work on Dover Street

Additional street work to install conduits will take place tomorrow (15th), Friday (16th), Monday (19th) and Tuesday (20th). The 700 block of Dover St. will be closed to traffic but the townhome parking lot will remain accessible from Fremont Ave. 

Monday, July 12, 2021

Car access to the 700 block of Dover St.

On Tuesday (July 13) and Wednesday (July 14), the 700 block of Dover St. will be blocked to allow for a sewer connection for 725 W. Pratt St. apartments. Residents who live on the corner of Fremont and Dover will still be able to access the parking lot behind their houses, but they must enter and exit from Fremont Ave. instead of Dover. The developer apologizes for the inconvenience.

Wednesday, June 30, 2021

Construction crane

The construction crane blocking Dover St. yesterday was not part of the 725 Pratt St. project. It evidently was there to repair roof damage on 730-734 Dover St., not related to the Zahlco development. Notifications concerning 725 Pratt St. will continue to be posted on this site.